St. Kitts Experiences Loss Of Power

St. Kitts Has Another Loss of Power Basseterre, St. Kitts – Nevis June 17, 2009 (CUOPM) An external fault on the Canada feeder (Conaree to Canada) led to a loss of electricity in some areas on Tuesday, the St. Kitts …

Read More

St. Kitts Suffers Power Outages…..Again

Rupture in cooling system causes power outage. Photo By Erasmus Williams Basseterre, St. Kitts – Nevis February 04, 2009 (CUOPM) Flooding as a result of a rupture in one of the cooling system of a generator at the Needsmust Power …

Read More

Unauthorized Settings Led To St. Kitts Blackout

Cabinet Meeting Officers Investigate Power Outages

Cabinet Meeting Officers Investigate Power Outages
Photo By Erasmus Williams

Basseterre, St. Kitts – Nevis
November 17, 2008 (CUOPM)

Two employees of the St. Kitts Electricity Services have been sent on leave after unauthorized system settings led to power outages on Friday and Saturday, hours after Minister of Public Works and Utilities, Dr. the Hon. Earl Asim Martin assured the general public of efforts to stabilise electricity generation and transmission to consumers.

The Cabinet, which convened a Special Session Monday to review this very disturbing development, said that the team of engineers was able to indicate precisely what resulted in the loss of electrical power in various sections of the island.

General Manager of the Electricity Department, Mr. John Channer in his report to the Cabinet, cited negligence on the part of staff members responsible for system protection matters at the power station as a reason for the outages.

“What was very concerning to the team of engineers was that system settings had been changed, adjusting what is called the “˜earth fault setting,’ without the guidance of the supervising engineers. In instances, it was not clear who made the setting changes. These changes in settings precipitated the development of electrical faults which led to the tripping of the generators,” said Minister of State for Infromation, Sen. the Hon. Nigel Carty in a Cabinet Statement issued late Monday afternoon.

Read More

St. Kitts Still Struggling With Power Outages

St. Kitts Department of Utilities Press Conference

St. Kitts Department of Utilities Press Conference
Photo By Erasmus Williams

Basseterre, St. Kitts
October 10, 2008 (SKNIS)

The Department of Utilities has been making “an all out effort” to repair damages caused by a fire to control panels and two generators at the Needsmust Power Station on October 2.

At a press conference on Thursday, Minister of Utilities Honourable Dr. Earl Asim Martin said the briefing ““ which was the second in a seven day span ““ was designed to give the media and the public a greater understanding of the issues and a tentative timeframe as to the resolution of the problem.

“When we met last week, I [noted] that we were actually generating 15 megawatts of electricity [after the fire],” he said, which is considerably less than the 24 megawatts needed to accommodate the demand for power during peak hours. “We also indicated that, at that point we were working [to bring another] Caterpillar engine online to provide additional capacity to the system.”

“I am pleased to report that the Caterpillar is online and is, providing 2.5 additional megawatts of electricity at this time,” Minister Martin said.